[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-719933":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},719933,398,1,"单选题","高层脚手架应安装防雷装置,可在脚手架一侧高杆接长,使之高出顶端()m作为接闪器。",[11,15,19],{"key":12,"text":13,"correct":14},"A","2",true,{"key":16,"text":17,"correct":18},"B","4",false,{"key":20,"text":21,"correct":18},"C","6","工地临时用电线路的架设及脚手架接地、避雷措施等，应按现行行业标准《施工现场临时用电安全技术规范》（JGJ 46）的有关规定执行。高层脚手架应安装防雷装置,可在脚手架一侧高杆接长,使之高出顶端2m作为接闪器。",{"id":6,"name":24,"category":25,"favorite":26},"登高架设","特种作业",0]