[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-715545":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":22},715545,390,1,"单选题","在高压电气设备上进行检修、试验、清扫、检查等工作时,需要全部停电或部分停电时应使用()。",[11,15,18],{"key":12,"text":13,"correct":14},"A","口头指令",false,{"key":16,"text":17,"correct":14},"B","第二种工作票",{"key":19,"text":20,"correct":21},"C","第一种工作票",true,"",{"id":6,"name":24,"category":25,"favorite":26},"高压电工","特种作业",0]