[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-715156":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":22},715156,390,1,"单选题","在全部停电和部分停电的电气设备上工作,必须完成的技术措施有()。",[11,15,18],{"key":12,"text":13,"correct":14},"A","停电;验电;放电;装设遮栏和悬挂标示牌",false,{"key":16,"text":17,"correct":14},"B","停电;放电;挂接地线;装设遮栏和悬挂标示牌",{"key":19,"text":20,"correct":21},"C","停电;验电;挂接地线;装设遮栏和悬挂标示牌",true,"在全部停电或部分停电的电气设备上工作时，必须完成下列保证安全的技术措施：⑴停电；⑵验电；⑶装设接地线；⑷悬挂标示牌和装设遮栏。上述措施由值班员执行。对于无经常值班人员的电气设备，由断开电源人执行，并应有监护人在场[两线一地制系统验电、装设接地线措施",{"id":6,"name":24,"category":25,"favorite":26},"高压电工","特种作业",0]