[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-715112":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":22},715112,390,1,"单选题","装设临时接地线的顺序是()。",[11,15,18],{"key":12,"text":13,"correct":14},"A","同时接接地端和设备导体部分",false,{"key":16,"text":17,"correct":14},"B","先接设备导体部分,后接接地端",{"key":19,"text":20,"correct":21},"C","先接接地端,后接设备导体部分",true,"高压回路上的工作中，关于接地线的移动或拆除《变电安规:4.4.11》规定如下：1.严禁工作人员擅自移动或拆除接地线。2.高压回路上的工作，需要拆除全部或一部分接地线后才能进行工作者，必须征得运行人员的许可(根据调度员指令装设的接地线，必须征得调度员的许可)，方可进行。3.工作完毕后，应立即恢复接地。《变电安规:4.4.9》规定：装设接地线必须先接接地端，后接导体端。拆4.接地线的顺序与此相反。接地线必须接触良好，连接应可靠。",{"id":6,"name":24,"category":25,"favorite":26},"高压电工","特种作业",0]