[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-671050":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},671050,384,1,"单选题","水压试验应在无损检测合格后进行；若需要作热处理的容器，则应()进行。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在热处理前",false,{"key":16,"text":17,"correct":14},"B","在热处理过程中",{"key":19,"text":20,"correct":21},"C","在热处理后",true,{"key":23,"text":24,"correct":14},"D","与热处理同时","",{"id":6,"name":27,"category":28,"favorite":29},"焊工（技师）","技能鉴定",0]