[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-712282":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":22},712282,382,1,"单选题","电缆线路工程验收必须按照()进行组织。",[11,15,18],{"key":12,"text":13,"correct":14},"A","中期验收和竣工验收2个阶段",false,{"key":16,"text":17,"correct":14},"B","初期验收、中期验收、竣工验收3个阶段",{"key":19,"text":20,"correct":21},"C","中间过程验收、自验收、预验收、竣工验收4个阶段",true,"",{"id":6,"name":24,"category":25,"favorite":26},"电力电缆","特种作业",0]