[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-712252":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},712252,382,1,"单选题","在北方地区敷设高压电缆时,冬天平均温度()以下,需要预先加热后再施工。",[11,15,19],{"key":12,"text":13,"correct":14},"A","0℃",true,{"key":16,"text":17,"correct":18},"B","-10℃",false,{"key":20,"text":21,"correct":18},"C","10℃","",{"id":6,"name":24,"category":25,"favorite":26},"电力电缆","特种作业",0]