[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-667626":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},667626,376,1,"单选题","施工架空线路交叉或平行接近其它带电线路时，为了防止感应电打人，工作前应在施工阶段( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","检查绝缘电阻",false,{"key":16,"text":17,"correct":18},"B","打好临时接地线",true,{"key":20,"text":21,"correct":14},"C","竖立警告牌",{"key":23,"text":24,"correct":14},"D","加防护栏","",{"id":6,"name":27,"category":28,"favorite":29},"电工（高级）","技能鉴定",0]