[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-666983":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},666983,375,1,"单选题","钢筋混凝土电杆的整体起吊的施工方案包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工方法及平面布置，操作注意事项",false,{"key":16,"text":17,"correct":14},"B","施工方法及平面布置，安全措施",{"key":19,"text":20,"correct":14},"C","施工方法及平面布置，操作注意事项，安全措施",{"key":22,"text":23,"correct":24},"D","施工方法及平面布置，工器具的选择，操作注意事项，安全措施",true,"",{"id":6,"name":27,"category":28,"favorite":29},"电工（中级）","技能鉴定",0]