[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-710861":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},710861,374,3,"判断题","依据《中国南方电网有限责任公司电力安全工作规程》，若待融冰的导线或地线位于杆塔同一侧垂直排列时，应先融下层，后融上层。 ( )",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"10.4.4.3 若待融冰的导线或地线位于杆塔同一侧垂直排列时，应先融上层，后融下层。",{"id":6,"name":21,"category":22,"favorite":23},"安规题库","特种作业",0]