[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-710730":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},710730,374,3,"判断题","依据《中国南方电网有限责任公司电力安全工作规程》，工作人员不应擅自移动或拆除接地线。 ( )",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"7.4.2.6 工作人员不应擅自移动或拆除接地线。高压回路上，需要拆除全部或一部分接地线后方能开始进行的工作，应征得运行人员或值班调度员的许可。工作完毕后立即恢复。",{"id":6,"name":21,"category":22,"favorite":23},"安规题库","特种作业",0]