[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-710497":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},710497,374,2,"多选题","依据《中国南方电网有限责任公司电力安全工作规程》，在同杆塔架设的多回线路上装设接地线时，应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先装上层、后装近侧",false,{"key":16,"text":17,"correct":18},"B","先装低压、后装高压",true,{"key":20,"text":21,"correct":18},"C","先装下层、后装上层",{"key":23,"text":24,"correct":18},"D","先装近侧、后装远侧","BCD","7.4.3.6 在同杆塔架设的多回线路上装设接地线时，应先装低压、后装高压，先装下层、后装上层，先装近侧、后装远侧。不应越过未经接地的线路对上层、远侧线路验电接地。拆除时次序相反。",{"id":6,"name":28,"category":29,"favorite":30},"安规题库","特种作业",0]