[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-710494":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":24,"analysis":25},710494,374,2,"多选题","依据《中国南方电网有限责任公司电力安全工作规程》，调度许可人办理调度检修申请单的作业终结前，应（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","确认作业现场自行装设的接地线已全部拆除",true,{"key":16,"text":17,"correct":14},"B","人员已全部撤离",{"key":19,"text":20,"correct":14},"C","设备恢复到调度管辖安全措施实施后的初始状态",{"key":22,"text":23,"correct":14},"D","所有现场工作票已办理工作票的终结","ABCD","6.10.2.3 调度许可人办理调度检修申请单的作业终结前，应确认作业现场自行装设的接地线已全部拆除、人员已全部撤离、设备恢复到调度管辖安全措施实施后的初始状态，所有现场工作票已办理工作票的终结。若其中个别工作票因故已办理工作延期且不影响送电的，可办理本调度检修申请单的作业终结。",{"id":6,"name":27,"category":28,"favorite":29},"安规题库","特种作业",0]