[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-710318":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":22},710318,374,1,"单选题","依据《中国南方电网有限责任公司电力安全工作规程》，融冰作业前，应确认待融冰线路（含导线、地线、OPGW光缆）及有关装置对塔身等接地体的距离满足（ ）的安全要求。",[11,15,19],{"key":12,"text":13,"correct":14},"A","带电作业",false,{"key":16,"text":17,"correct":18},"B","融冰电压不击穿",true,{"key":20,"text":21,"correct":14},"C","绝缘遮蔽","10.4.4.1 融冰作业前，应确认待融冰线路（含导线、地线、OPGW光缆）及有关装置对塔身等接地体的距离满足融冰电压不击穿的安全要求。",{"id":6,"name":24,"category":25,"favorite":26},"安规题库","特种作业",0]