[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-710246":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},710246,374,1,"单选题","依据《中国南方电网有限责任公司电力安全工作规程》，在高低压线路同杆塔架设的低压带电线路上工作时，应先检查与高压线的距离，（ ）。在下层低压带电导线未采取绝缘隔离措施或未停电接地时，作业人员不应穿越。",[11,15,19],{"key":12,"text":13,"correct":14},"A","采取防止误碰带电高压设备的措施",true,{"key":16,"text":17,"correct":18},"B","采取防感应电的措施",false,{"key":20,"text":21,"correct":18},"C","采用绝缘遮蔽措施","16.5.2.5 在高低压线路同杆塔架设的低压带电线路上工作时，应先检查与高压线的距离，采取防止误碰带电高压设备的措施。在下层低压带电导线未采取绝缘隔离措施或未停电接地时，作业人员不应穿越。",{"id":6,"name":24,"category":25,"favorite":26},"安规题库","特种作业",0]