[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-710231":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},710231,374,1,"单选题","依据《中国南方电网有限责任公司电力安全工作规程》，挖掘出的电缆或接头盒，如下面需要挖空时，应采取（ ）。电缆悬吊应每1m～1.5m吊一道；接头盒悬吊应平放，不得使接头盒受到拉力；若电缆接头无保护盒，应做好充分保护措施，方可悬吊。",[11,15,19],{"key":12,"text":13,"correct":14},"A","悬吊保护措施",true,{"key":16,"text":17,"correct":18},"B","固定保护措施",false,{"key":20,"text":21,"correct":18},"C","隔离保护措施","15.2.7 挖掘出的电缆或接头盒，如下面需要挖空时，应采取悬吊保护措施。电缆悬吊应每1m～1.5m吊一道；接头盒悬吊应平放，不得使接头盒受到拉力；若电缆接头无保护盒，应做好充分保护措施，方可悬吊。",{"id":6,"name":24,"category":25,"favorite":26},"安规题库","特种作业",0]