[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-639305":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},639305,340,2,"多选题","工业金属管道工程的质量验收，可按（）进行划分。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分项工程",true,{"key":16,"text":17,"correct":14},"B","分部（子分部）工程",{"key":19,"text":20,"correct":14},"C","单位（子单位）工程",{"key":22,"text":23,"correct":24},"D","其他选项都不是",false,"ABC","",{"id":6,"name":28,"category":29,"favorite":30},"D1压力管道巡检维护","特种作业",0]