[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-606748":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":22},606748,307,1,"单选题","提升机剁绳头或缩绳根后,必须经过()以上额定负荷提升试验后方可正式运转。",[11,15,18],{"key":12,"text":13,"correct":14},"A","5次",false,{"key":16,"text":17,"correct":14},"B","4次",{"key":19,"text":20,"correct":21},"C","3次",true,"",{"id":6,"name":24,"category":25,"favorite":26},"煤矿主提升机操作作业","安全生产",0]