[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-604950":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},604950,304,1,"单选题","穿过含水层段的井巷工程,应按防水要求进行()处理。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","壁后注浆",true,{"key":16,"text":17,"correct":18},"B","加强支护",false,{"key":20,"text":21,"correct":18},"C","锚喷",{"key":23,"text":24,"correct":18},"D","喷浆","",{"id":6,"name":27,"category":28,"favorite":29},"煤矿探放水作业","安全生产",0]