[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-595808":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},595808,295,1,"单选题","为防止巷道贯通时发生事故，综合机械化掘巷道在相距( )米前，必须停止一个工作面作业，做好调整通风系统的准备工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","50",true,{"key":16,"text":17,"correct":18},"B","30",false,{"key":20,"text":21,"correct":18},"C","60",{"key":23,"text":24,"correct":18},"D","20","",{"id":6,"name":27,"category":28,"favorite":29},"掘进班组长","安全生产",0]