[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-595598":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},595598,295,1,"单选题","炮掘工作面在贯通前( )，必须停止一个工作面作业，做好调整通风系统的准备工作。",[11,15,19],{"key":12,"text":13,"correct":14},"A","20m",true,{"key":16,"text":17,"correct":18},"B","30m",false,{"key":20,"text":21,"correct":18},"C","50m","",{"id":6,"name":24,"category":25,"favorite":26},"掘进班组长","安全生产",0]