[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-571361":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":22},571361,268,1,"单选题","为了加强对重大危险源控制系统的监管,对于新建项目的重大危险、有害设施,企业应在该项目()提交重大危险源安全评估报告。",[11,15,18],{"key":12,"text":13,"correct":14},"A","设计审查后",false,{"key":16,"text":17,"correct":14},"B","开工建设前",{"key":19,"text":20,"correct":21},"C","投入运行前",true,"",{"id":6,"name":24,"category":25,"favorite":26},"金属冶炼(铜冶炼)","安全生产",0]