[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-567922":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":22},567922,264,1,"单选题","工艺设备的强度不足以承受完全发展的内部粉尘爆炸产生的压力时,必须设置()。",[11,15,19],{"key":12,"text":13,"correct":14},"A","压力表",false,{"key":16,"text":17,"correct":18},"B","泄爆口",true,{"key":20,"text":21,"correct":14},"C","防爆墙","",{"id":6,"name":24,"category":25,"favorite":26},"金属冶炼(镁及镁合金制造与铸造)","安全生产",0]