[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-564298":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":22},564298,260,1,"单选题","采石场上部需要剥离的,剥离工作面应当超前于开采工作面()m以上。",[11,15,18],{"key":12,"text":13,"correct":14},"A","8",false,{"key":16,"text":17,"correct":14},"B","6",{"key":19,"text":20,"correct":21},"C","4",true,"",{"id":6,"name":24,"category":25,"favorite":26},"金属非金属-小型露天采石场","安全生产",0]