[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-562831":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},562831,258,3,"判断题","井下作业时,因漏电保护装置动作切断供电电源,当合闸送电后仍漏电跳闸,造成不能送电的情况下,为不影响生产可将漏电保护装置暂时撤除。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"",{"id":6,"name":21,"category":22,"favorite":23},"金属非金属-地下矿山","安全生产",0]