[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-529825":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},529825,237,1,"单选题","当非关键工作M正在实施时，检查进度计划发现工作M存在的进度偏差不影响总工期，但影响后续承包商工作的进度，调整进度计划的首选方法是缩短（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","后续工作的持续时间",false,{"key":16,"text":17,"correct":18},"B","工作M的持续时间",true,{"key":20,"text":21,"correct":14},"C","工作M平行工作的持续时间",{"key":23,"text":24,"correct":14},"D","关键工作的持续时间","",{"id":6,"name":27,"category":28,"favorite":29},"图书专业 (军队文职)","公务员",0]