[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-529641":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},529641,237,1,"单选题","对项目进行总结后，项目经理发现按进度计划要花28000小时，已经挣得25000小时，支付26000小时，正确结论应该是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目的成本效率非常高",false,{"key":16,"text":17,"correct":14},"B","需要趋势分析报告",{"key":19,"text":20,"correct":21},"C","项目滞后于进度计划",true,{"key":23,"text":24,"correct":14},"D","项目超前于进度计划","",{"id":6,"name":27,"category":28,"favorite":29},"图书专业 (军队文职)","公务员",0]