[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-529594":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},529594,237,1,"单选题","在项目进度控制中，（ ）不适合于缩短活动工期。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","准确确定项目进度的当前状态",true,{"key":16,"text":17,"correct":18},"B","投入更多的资源",false,{"key":20,"text":21,"correct":18},"C","改进技术",{"key":23,"text":24,"correct":18},"D","缩减活动范围","",{"id":6,"name":27,"category":28,"favorite":29},"图书专业 (军队文职)","公务员",0]