[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-529586":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},529586,237,1,"单选题","某公司承担了某市政府门户网站的建设项目，与该市信息中心签订了合同。在设计页面的过程中，经过多轮讨论和修改，页面在两周前终于得到了信息中心的认可，项目进入开发实施阶段。然而，信息中心本周提出，分管市领导看到页面设计后不是很满意，要求重新设计页面。但是，如果重新设计页面，可能会影响项目工期，无法保证网站按时上线。在这种情况下，项目经理最恰当的做法是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","坚持原设计方案，因为原页面已得到客户认可",false,{"key":16,"text":17,"correct":14},"B","让设计师加班加点，抓紧时间修改页面",{"key":19,"text":20,"correct":14},"C","向领导争取网站延期上线，重新设计页面",{"key":22,"text":23,"correct":24},"D","评估潜在的工期风险，再决定采取何种应对措施",true,"",{"id":6,"name":27,"category":28,"favorite":29},"图书专业 (军队文职)","公务员",0]