[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-529529":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},529529,237,1,"单选题","一个投资额为3000万的大型信息化软件开发项目，承建单位计划投入100人，其中包括测试工程师30人。需求分析完成并通过确认后，监理方对承建单位提交的测试工作计划进行了评审，以下做法不正确的是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","审核测试计划中对软件测试的资源投入、时间安排等的合理性与可行性",false,{"key":16,"text":17,"correct":14},"B","审查测试计划中软件测试环境能否满足测试工作的需要",{"key":19,"text":20,"correct":21},"C","抽查测试计划中测试用例是否正确",true,{"key":23,"text":24,"correct":14},"D","审查所进行的测试类型能否满足测试需求","",{"id":6,"name":27,"category":28,"favorite":29},"图书专业 (军队文职)","公务员",0]