[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-529524":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},529524,237,1,"单选题","某软件开发项目合同规定，需求分析要经过客户确认后方可进行软件设计。但建设单位以客户代表出国、其他人员不知情为由拒绝签字，造成进度延期。软件开发单位进行索赔一般按（ ）顺序较为妥当①由该项目的监理方进行调解②由经济合同仲裁委员会仲裁③由有关政府主管机构仲裁",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①②③",false,{"key":16,"text":17,"correct":18},"B","①③②",true,{"key":20,"text":21,"correct":14},"C","③①②",{"key":23,"text":24,"correct":14},"D","②①③","",{"id":6,"name":27,"category":28,"favorite":29},"图书专业 (军队文职)","公务员",0]