[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-529522":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},529522,237,1,"单选题","已知某工程网络计划中工作M的自由时差为3天，总时差为5天。监理工程师在检查进度时发现该工作的实际进度拖延，且影响工程总工期1天。在其他工作均正常的前提下，工作M的实际进度比计划进度拖延了（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":14},"C","5",{"key":22,"text":23,"correct":24},"D","6",true,"",{"id":6,"name":27,"category":28,"favorite":29},"图书专业 (军队文职)","公务员",0]