[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-529511":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},529511,237,1,"单选题","如果一个工作包的估算成本为1500元且完成日期为今天，但今天已花费成本为1350元却只完成三分之二的工作，这时成本偏差为（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","150元",false,{"key":16,"text":17,"correct":14},"B","-150元",{"key":19,"text":20,"correct":21},"C","-350元",true,{"key":23,"text":24,"correct":14},"D","-500元","",{"id":6,"name":27,"category":28,"favorite":29},"图书专业 (军队文职)","公务员",0]