[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-515647":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},515647,230,2,"多选题","下列关于建设工程施工合同上的竣工与验收的表述中，符合合同法律制度规定的有()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设工程未经竣工验收合格，不得交付使用",true,{"key":16,"text":17,"correct":18},"B","建设工程经竣工验收合格的，以建设工程转移占有之日为竣工日期",false,{"key":20,"text":21,"correct":18},"C","建设工程未经竣工验收，发包人即擅自使用的，以发包人开始使用之日为竣工日期",{"key":23,"text":24,"correct":14},"D","承包人已提交竣工验收报告，发包人拖延验收的，以提交验收报告之日为竣工日期","AD","",{"id":6,"name":28,"category":29,"favorite":30},"审计学 (军队文职)","公务员",0]