[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-515358":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},515358,230,1,"单选题","新建或扩建项目第一批购买的不够固定资产规格的工具、器具和生产家具的费用是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设备安装工程费用",false,{"key":16,"text":17,"correct":14},"B","建筑工程费用",{"key":19,"text":20,"correct":14},"C","设备购置费",{"key":22,"text":23,"correct":24},"D","工器具及生产家具购置费用",true,"",{"id":6,"name":27,"category":28,"favorite":29},"审计学 (军队文职)","公务员",0]