[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-515340":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":28},515340,230,1,"单选题","建设项目管理中的业主的进度目标指的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目动用的时间目标",true,{"key":16,"text":17,"correct":18},"B","工厂建成可以投入生产",false,{"key":20,"text":21,"correct":18},"C","道路建成可以通车",{"key":23,"text":24,"correct":18},"D","办公楼可以启用",{"key":26,"text":27,"correct":18},"E","旅馆可以开业","",{"id":6,"name":30,"category":31,"favorite":32},"审计学 (军队文职)","公务员",0]