[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-515323":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},515323,230,1,"单选题","合同中没有适用或类似变更工程的价格，则变更部分的价款调整应该（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按审价部门提出的价格调整",false,{"key":16,"text":17,"correct":14},"B","按发包人指定的价格调整",{"key":19,"text":20,"correct":14},"C","按设计部门提出的价格调整",{"key":22,"text":23,"correct":24},"D","由承包人或发包人提出适当的变更价格，经对方确认后调整",true,"",{"id":6,"name":27,"category":28,"favorite":29},"审计学 (军队文职)","公务员",0]