[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-515283":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},515283,230,1,"单选题","下列阶段不属于我国现行的工程建设程序内容的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设前期阶段",false,{"key":16,"text":17,"correct":14},"B","准备阶段",{"key":19,"text":20,"correct":14},"C","施工阶段",{"key":22,"text":23,"correct":24},"D","质量保修期过后的房屋改造",true,"",{"id":6,"name":27,"category":28,"favorite":29},"审计学 (军队文职)","公务员",0]