[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-513922":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},513922,230,1,"单选题","投标截止时间之后至投标有效期满之前，投标人对投标文件的任何补充、修改，招标人( )接受。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","可以",false,{"key":16,"text":17,"correct":14},"B","应当",{"key":19,"text":20,"correct":21},"C","不予",true,{"key":23,"text":24,"correct":14},"D","适当","《招标投标法》第29条规定，投标人在招标文件要求提交投标文件的截止时间之前，可以补充、修改或者撤回已提交的投标文件，并书面通知招标人。投标截止时间之后至投标有效期满之前，投标人对投标文件的任何补充、修改，招标人不予接受，撤回投标文件的还将被没收投标保证金。",{"id":6,"name":27,"category":28,"favorite":29},"审计学 (军队文职)","公务员",0]