[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-504750":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},504750,225,1,"单选题","建设单位应当自领取施工许可证之日起()内开工。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1个月",false,{"key":16,"text":17,"correct":14},"B","2个月",{"key":19,"text":20,"correct":21},"C","3个月",true,{"key":23,"text":24,"correct":14},"D","5个月","建设单位应当自领取施工许可证之日起3个月内开工。因故不能按期开工的，应当向发证机关申请延期；延期以两次为限，每次不超过3个月。既不开工又不申请延期或者超过延期时限的，施工许可证自行废止。",{"id":6,"name":27,"category":28,"favorite":29},"经济学 (军队文职)","公务员",0]