[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-501421":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},501421,223,1,"单选题","若某投资项目的投资期为零，则直接利用年金现值系数计算该项目内含报酬率指标所要求的前提条件是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投产后净现金流量为普通年金形式",true,{"key":16,"text":17,"correct":18},"B","投产后净现金流量为递延年金形式",false,{"key":20,"text":21,"correct":18},"C","投产后各年的净现金流量不相等",{"key":23,"text":24,"correct":18},"D","在建设起点没有发生任何投资","利用年金现值系数直接计算内含报酬率的方法适用的条件是：全部原始投资额(C)在建设起点(0时点)一次性投入，且投资期为0，投产后至项目终结时，各年现金净流量(NCF)均相等，即符合普通年金形式。",{"id":6,"name":27,"category":28,"favorite":29},"会计学 (军队文职)","公务员",0]