[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-501267":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},501267,223,1,"单选题","某企业拟进行一项存在一定风险的完整工业项目投资，有甲、乙两个方案可供选择：已知甲方案净现值的期望值为1000万元，标准离差为300万元；乙方案净现值的期望值为1200万元，标准离差为330万元。下列结论中正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","甲方案优于乙方案",false,{"key":16,"text":17,"correct":18},"B","甲方案的风险大于乙方案",true,{"key":20,"text":21,"correct":14},"C","甲方案的风险小于乙方案",{"key":23,"text":24,"correct":14},"D","无法评价甲、乙方案的风险大小","由于甲、乙方案净现值的期望值不同，所以不能直接根据标准离差来比较两个方案风险的大小，需要比较标准离差率。甲方案净现值的标准离差率=300\u002F1000=0.3；乙方案净现值的标准离差率=330\u002F1200=0.275。由于甲方案净现值的标准离差率高于乙方案净现值的标准离差率，因此甲方案的风险大于乙方案，",{"id":6,"name":27,"category":28,"favorite":29},"会计学 (军队文职)","公务员",0]