[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-501210":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},501210,223,1,"单选题","某公司全年需用X材料18000件，计划开工360天。该材料订货日至到货日的时间为5天，保险储备量为100件。该材料的再订货点是()件。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","100",false,{"key":16,"text":17,"correct":14},"B","150",{"key":19,"text":20,"correct":14},"C","250",{"key":22,"text":23,"correct":24},"D","350",true,"再订货点=预计交货期内的需求+保险储备，预计交货期内的需求=18000\u002F360×5=250(件)，因此，再订货点=250+100=350(件)。",{"id":6,"name":27,"category":28,"favorite":29},"会计学 (军队文职)","公务员",0]