[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-500386":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},500386,223,1,"单选题","总承包人乙公司经发包人甲公司同意，将自己承包的部分建设工程分包给丙公司。因丙公司完成的工程质量出现问题，给甲公司造成200万元的经济损失。有关甲公司所受的经济损失，下列表述正确的是()",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","由丙公司承担赔偿责任",false,{"key":16,"text":17,"correct":14},"B","由乙公司承担赔偿责任",{"key":19,"text":20,"correct":14},"C","首先由丙公司承担赔偿责任，不足部分由乙公司承担",{"key":22,"text":23,"correct":24},"D","由乙公司和丙公司承担连带赔偿责任",true,"(1)经发包人同意，总承包人可以将自己承包的“部分工作”交由第三人完成；(2)第三人就其完成的工作成果与总承包人向发包人承担连带责任。",{"id":6,"name":27,"category":28,"favorite":29},"会计学 (军队文职)","公务员",0]