[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-477692":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},477692,214,1,"单选题","项目执行期间重新委任了一名项目经理，项目已经按照计划执行，但是项目经理发现客户对报告方法相当不满，项目经理应该首先（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","检查沟通系统",false,{"key":16,"text":17,"correct":18},"B","询问客户的不满和要求，找出解决方案",true,{"key":20,"text":21,"correct":14},"C","向客户建议修改报告",{"key":23,"text":24,"correct":14},"D","让项目团队制订替代方案","",{"id":6,"name":27,"category":28,"favorite":29},"档案专业 (军队文职)","公务员",0]