[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-477089":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},477089,214,1,"单选题","项目经理在进行项目质量规范时应设计出符合项目要求的质量管理流程和标准，由此而产生的质量成本属于（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","纠错成本",false,{"key":16,"text":17,"correct":18},"B","预防成本",true,{"key":20,"text":21,"correct":14},"C","评估成本",{"key":23,"text":24,"correct":14},"D","缺陷成本","",{"id":6,"name":27,"category":28,"favorite":29},"档案专业 (军队文职)","公务员",0]