[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-477055":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},477055,214,1,"单选题","活动持续时间估算中，不能包括下列哪个？（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在下一个活动的开始时间与本活动的结束时间之间的时间",true,{"key":16,"text":17,"correct":18},"B","完成本活动所需的工作时段数",false,{"key":20,"text":21,"correct":18},"C","时间的可能变动区间",{"key":23,"text":24,"correct":18},"D","存在不确定性的工作时段数估计","",{"id":6,"name":27,"category":28,"favorite":29},"档案专业 (军队文职)","公务员",0]