[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-477042":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},477042,214,1,"单选题","如果在挣值分析中，出现进度和成本偏差，CV＞0.SV＜0说明的情况是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目成本节约、进度落后",true,{"key":16,"text":17,"correct":18},"B","项目成本超支、进度落后",false,{"key":20,"text":21,"correct":18},"C","项目成本超支、进度超前",{"key":23,"text":24,"correct":18},"D","项目成本节约、进度超前","",{"id":6,"name":27,"category":28,"favorite":29},"档案专业 (军队文职)","公务员",0]