[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-449455":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},449455,209,1,"单选题","建筑物的沉降观测是依据埋设在建筑物附近的水准点进行的，为了相互校并防止由于某个水准点的高程变动造成差错，一般至少埋设水准点的数量为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2个",false,{"key":16,"text":17,"correct":18},"B","3个",true,{"key":20,"text":21,"correct":14},"C","6个",{"key":23,"text":24,"correct":14},"D","10个以上","沉降观测采用几何水准测量或液体静力水准测量。在几何水准测量中，为了保证准确性，水准点不得少于3个，应埋设在变形区以外的稳固处，冰冻区应埋设在冻土层以下0.5m；为了提高观测精度，水准点和观测点不能相距太远。观测点的数量和位置应能全面反映建筑物的变形情况，一般是均匀设置，但在荷载有变化的部位、平面形状变化处、沉降缝两侧、具有代表性的支柱和基础上，应加设足够的观测点。",{"id":6,"name":27,"category":28,"favorite":29},"土木建筑类 (电网)","公务员",0]