[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-438174":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},438174,203,1,"单选题","假设—条指令的执行过程可以分为“取指令”、“分析”和“执行”三段，每—段分别只有—个部件可供使用，并且执行时间分别为 Δt、2Δt 和 3Δt，连续执行 n 条指令所需要花费的最短时间约为（ ）。（假设“取指令”、“分析”和“执行”可重叠，并假设 n 足够大）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","6nΔt",false,{"key":16,"text":17,"correct":14},"B","2nΔt",{"key":19,"text":20,"correct":21},"C","3nΔt",true,{"key":23,"text":24,"correct":14},"D","nΔt","依题意，将一条指令分成 3 段，则每段所需时间为 T=3Δt，假设 n 足够大，则在采用流水线技术时，相当于每隔 T 时间就能得到一条指令的处理结果，那么连续执行 n 条指令所需要花费的最短时间约为 nT=3nΔt。",{"id":6,"name":27,"category":28,"favorite":29},"计算机 (电网)","公务员",0]